Work package readiness: determine whether a specific unit of physical work can begin now. When it cannot, say which gate is open and who owns it.

  • Records
  • Released work
  • Physical build
  • Human authority

What happensA long-lead supplier slips. The kit breaks, the block loses its sequence, and the crew needs a stop-or-proceed call that will hold up.

  1. The kit goes short, Records

    Two of the nine spools for WP-019 are in stores, made to Rev C, and Rev D re-specifies them. Purchasing counts them as stock. The work package cannot use them.

  2. Readiness recomputes, Records

    Configuration and material are known open. Six gates, two of them open: NOT READY.

  3. The package cannot release, Released work

    The crew booked against WP-019 has no releasable work at the bench, and the schedule still shows it starting this shift.

  4. The consequence reaches steel

    The block loses its window, Physical build

    The outfitting access on block B30 is a finite window. It moves, and every package sequenced behind it moves with it.

  5. A named person holds, or proceeds, Human authority

    Production release authority for B30 accepts the open gate in writing, or holds. VeldBuild computes the verdict; it does not release the work.

What it costsA crew either mobilizes against buildable work or loses a shift to a blocked gate, mid-work stoppage, or avoidable rework.

How VeldBuild answers it

Can WP-019 begin now? If not, which gate is open?

What it reads

Scope
One work package, its governing revision, declared predecessors, material kit, access state, quality gates, and assigned resources at a stated time.
Records
Work package scope and effective revision · Material kit and receipt acceptance state · Predecessor completion and acceptance · Area / zone release · Quality hold points and open nonconformances · Assigned trade and crew
Evidence it needs
Configuration release record · Material acceptance record · Predecessor acceptance record · Inspection plan and nonconformance state

What it computes

Steps
  • Check each of the six readiness gates against its record
  • Never average an unknown into a yes
  • Name the reason and the owner of the gate that holds
Output
Ready, not ready or cannot establish; the gates that hold it, their evidence, and who must clear each.

What stays with people

Left unknown
  • Missing, stale, or conflicting evidence
  • Unestablished applicability or effectivity
  • A gate with no attributable source or owner
Decided by
  • VeldBuild computes the verdict from evidence; it does not waive a gate by assertion
  • A named production authority releases the physical work

What would prove it on real records

Test
Connect a bounded live work-package slice, compare verdicts with authorized human releases, and review false-ready, false-blocked, and cannot-establish cases.
  1. Which readiness gate is binding, and who owns it?
  2. What has to change for the verdict to become Ready?

If your team answers this by hand, start with one work area.

Email the release decision, the systems that hold its records, and who owns it. Keep the first message non-confidential.